How to Run a 60-Minute SMED Assessment (Without Over Complicating It)

Changeover time is one of the fastest ways to recover capacity without buying equipment. Yet many SMED efforts fail because they become overly complex.
This post shows a simple, 60-minute assessment you can run to identify immediate changeover wins.
Understanding SMED
What is SMED?
SMED (Single-Minute Exchange of Dies) is a method to reduce changeover time by separating tasks into:
Internal work: must happen while equipment is stopped
External work: can happen while equipment is running
The goal is to convert internal work into external work wherever possible.
The 60-Minute SMED Assessment
Step 1: Record the Changeover (10 minutes)
Use a phone video. Don’t stage anything. Capture reality.
Step 2: Break the steps into a timeline (15 minutes)
Write each step with timestamps.
Step 3: Label Internal vs External (10 minutes)
Highlight what can be done beforehand.
Step 4: Identify “searching” and “walking” waste (10 minutes)
These are often the biggest easy wins.
Step 5: Pick 3 immediate improvements (10 minutes)
Examples:
pre-stage tools and parts
standardize clamps/fasteners
create setup kits
add visual cues
Step 6: Assign an owner + date (5 minutes)
No owner, no change.
Best Practices
Start with a 20–30% reduction target
Standardize the new method
Train the team
Repeat on the next high-impact changeover
Conclusion
SMED doesn’t need a complex program. A simple assessment + fast follow-through can recover significant capacity within weeks.